Construction Status at 3001 Minnesota

 

 

C=Complete, N/A =Not Applicable

IP= In Progress, SUB=Subcontract

Click on each topic to see a photo associated with it.

1. Lot Purchase C Circa mid 2007
2. Blueprints C April 2008
3.  Building Permits C April 2008
4.  Basement Excavation (sub) C April 14, 2008
5.  Basement Walls (sub) C April 23, 2008
6. Slab Floor (sub) C
7.  Sewer/Water Lateral (sub)  
8.  Electrical Pedestal (sub) C Circa May 26, 2008
9.  Gas Hookup (sub)  
10.  Basement Ext. Insulation C April 25, 2008
11. Floor Deck Installed N/A
12. Exterior Wall/Sheathing C
13. Roof Trusses June 13, 2008
14. Roof Sheathing June 18, 2008
15. Roofing Felt, Ice Guard June 21, 2008
16. Shingles C July 9, 2008
17. Windows Installed C July 30, 2008
18. Insulation/Vapor Barrier C
19. Exterior Entry Doors C August 1, 2008
20. Soffit/Fascia C
21. Siding C August 23, 2008
22. Rough Plumbing (sub) C about August 12, 2008
23. Rough Electrical (sub) C August 20, 2008
24. HVAC Installed (sub) C Late October, 2008
25. Drywall Hung C October 4, 2008
26. Attic Insulation C
27. Drywall Finished (sub) C
28. Trim and Int. Doors C November 21, 2008
29. Floor Covering-Vinyl (sub) C November 1, 2008
30. Cabinets and Countertops C November 15, 2008
31. Floor Covering-Carpet (sub) C November 21, 2008
32. Finish Plumbing (sub) C November 13, 2008
33. Finish Electric (sub) C November 24, 2008
   
35. Driveway (sub) C Mid October, 2008
36. Sidewalk (sub) C Mid October, 2008
37. Landscaping C May 2, 2009
38. Other  
39.FINISHED!! C May 2, 2009