C=Complete, N/A =Not Applicable
IP= In Progress, SUB=Subcontract
Click on each
topic to see a photo associated with it.
| 1.
Lot Purchase |
C August, 2004 |
| 2. Building Permits |
C August 10, 2004 |
| 3.
Basement Excavation (sub) |
C August 24, 2004 |
| 4. Basement Walls (sub) |
C August 26, 2004 |
| 5. Basement Floor (sub) |
C Sept. 3, 2004 |
| 6. Sewer/Water Lateral (sub) |
C August 25, 2004 |
| 7. Electrical Pedestal (sub) |
C Oct. 12, 2004 |
| 8. Gas Hookup (sub) |
C Sept. 27, 2004 |
| 9. Basement Ext. Insulation |
C August 28, 2004 |
| 10.
Floor Deck Installed |
C Sept. 25, 2004 |
| 11.
Exterior Wall/Sheathing,
Ground Floor/
Main Floor/ Top Floor |
C
9-18 /
C
/
C |
| 12.
Roof Trusses |
C
Oct. 16, 2004 |
| 13. Roof Sheathing |
C Oct. 30, 2004 |
| 14. Roofing Felt, Ice Guard |
C Nov. 5, 2004 |
| 15. Shingles |
C Nov. 10, 2004 |
| 16. Windows Installed |
C Jan. 28, 2005 |
| 17. Insulation/Vapor Barrier |
C Jan. 22, 2005 |
| 18. Exterior Entry Doors |
C Jan, 21, 2005 |
| 19. Soffit/Fascia |
C April 30, 2005 |
| 20. Siding |
C April 30, 2005 |
| 21.
Rough Plumbing (sub) |
C Nov 17, 2004 |
| 22. Rough Electrical (sub) |
C Jan. 14, 2005 |
| 23. HVAC Installed (sub) |
C March 1, 2005 |
| 24. Drywall Hung |
C Feb. 5,
2005 |
| 25. Attic Insulation |
Completed December 30,
2004 |
| 26. Drywall Finished (sub) |
Completed February 19, 2005 |
| 27. Trim and Int. Doors |
C (doors) March 5
C. May 27, 2005 |
| 28. Floor Covering-Vinyl (sub) |
C May 11, 2005 |
| 29. Cabinets and Countertops |
C April 30, 2005 |
| 30. Floor Covering-Carpet (sub) |
C May 11, 2005 |
| 31. Finish Plumbing (sub) |
C May 5, 2005 |
| 32. Finish Electric (sub) |
C May 5, 2005 |
| 33. Ext Decks |
C May 23, 2005 |
| 34. Driveway (sub) |
C May 23, 2005 |
| 35. Sidewalk (sub) |
C May 23, 2005 |
| 35. Landscaping |
C May 21, 2005 |
| 36. Other |
C |
| 36.FINISHED!! |
C May 27, 2005 THANK
YOU!!!!!!!!! |
|