1.  Lot Purchase C August, 2004
2.  Building Permits C August 10, 2004
3.  Basement Excavation (sub) C August 24, 2004
4.  Basement Walls (sub) C August 26, 2004
5.  Basement Floor (sub) C Sept. 3, 2004
6.  Sewer/Water Lateral (sub) C August 25, 2004
7.  Electrical Pedestal (sub) C Oct. 12, 2004
8.  Gas Hookup (sub) C Sept. 27, 2004
9.  Basement Ext. Insulation C August 28, 2004
10. Floor Deck Installed C Sept. 25, 2004
11. Exterior Wall/Sheathing, Ground Floor/ Main Floor/ Top Floor C 9-18 / C / C
12. Roof Trusses C Oct. 16, 2004
13. Roof Sheathing C Oct. 30, 2004
14. Roofing Felt, Ice Guard C Nov. 5, 2004
15. Shingles C Nov. 10, 2004
16. Windows Installed C Jan. 28, 2005
17. Insulation/Vapor Barrier C Jan. 22, 2005
18. Exterior Entry Doors C Jan, 21, 2005
19. Soffit/Fascia C April 30, 2005
20. Siding C April 30, 2005
21. Rough Plumbing (sub) C Nov 17, 2004
22. Rough Electrical (sub) C Jan. 14, 2005
23. HVAC Installed (sub) C March 1, 2005
24. Drywall Hung C Feb. 5, 2005
25. Attic Insulation Completed December 30, 2004
26. Drywall Finished (sub) Completed February 19, 2005
27. Trim and Int. Doors C (doors) March 5     C. May 27, 2005
28. Floor Covering-Vinyl (sub) C May 11, 2005
29. Cabinets and Countertops C April 30, 2005
30. Floor Covering-Carpet (sub) C May 11, 2005
31. Finish Plumbing (sub) C May 5, 2005
32. Finish Electric (sub) C May 5, 2005
33. Ext Decks C May 23, 2005
34. Driveway (sub) C May 23, 2005
35. Sidewalk (sub) C May 23, 2005
35. Landscaping C May 21, 2005
36. Other C
36.FINISHED!! C May 27, 2005  THANK YOU!!!!!!!!!