CONSTRUCTION STATUS AT 1008 Franklin

 

C=Complete, N/A =Not Applicable

IP= In Progress, SUB=Subcontract

Click on each topic to see a photo associated with it.

1. Lot Purchase C. February 4, 2005
2. Blueprints C. circa April 15, 2005
3.  Building Permits C. circa April 19, 2005
4.  Basement Excavation (sub) C. May 13, 2004
5.  Basement Walls (sub) C. May 20, 2005
6.  Basement Floor (sub) C. May 24, 2005
7.  Sewer/Water Lateral (sub) C May 11, 2005
8.  Electrical Pedestal (sub) C June 14, 2005
9.  Gas Hookup (sub) C June 15, 2005
10.  Basement Ext. Insulation C June 2, 2005
11. Floor Deck Installed C June 4, 2005
12. Exterior Wall/Sheathing C July 2, 2005
13. Roof Trusses C July 16, 2005
14. Roof Sheathing C July 30, 2005
15. Roofing Felt, Ice Guard C July 30, 2005.
16. Shingles C September 9, 2005
17. Windows Installed C Aug 13, 2005
18. Insulation/Vapor Barrier C. October 29, 2005
19. Exterior Entry Doors C August 13, 2005
20. Soffit/Fascia C October 10, 2005
21. Siding C October 1, 2005
22. Rough Plumbing (sub) C August 11, 2005
23. Rough Electrical (sub) C August 11, 2005
24. HVAC Installed (sub) C January, 27, 2006
25. Drywall Hung C October 29, 2005
26. Attic Insulation C November 1, 2005
27. Drywall Finished (sub) C December 7, 2005
28. Trim and Int. Doors C January 28, 2006
29. Floor Covering-Vinyl (sub) C January 22, 2006
30. Cabinets and Countertops C January 22, 2006
31. Floor Covering-Carpet (sub) C January 26, 2006
32. Finish Plumbing (sub) C January 23, 2006
33. Finish Electric (sub) C January 23, 2006
34. Ext Decks C
35. Driveway (sub) C
36. Sidewalk (sub) C
37. Landscaping C August 19, 2006
38. Other  
39.FINISHED!! C August 19, 2006