|
C=Complete, N/A =Not Applicable
IP= In Progress, SUB=Subcontract
Click on each
topic to see a photo associated with it.
| 1.
Lot Purchase |
C. February 4, 2005 |
| 2.
Blueprints |
C. circa April 15, 2005 |
| 3. Building Permits |
C. circa April 19, 2005 |
| 4.
Basement Excavation (sub) |
C. May 13, 2004 |
| 5. Basement Walls (sub) |
C. May 20, 2005 |
| 6. Basement Floor (sub) |
C. May 24, 2005 |
| 7. Sewer/Water Lateral (sub) |
C May 11, 2005 |
| 8. Electrical Pedestal (sub) |
C June 14, 2005 |
| 9. Gas Hookup (sub) |
C June 15, 2005 |
| 10. Basement Ext. Insulation |
C June 2, 2005 |
| 11.
Floor Deck Installed |
C June 4, 2005 |
| 12.
Exterior Wall/Sheathing |
C July 2, 2005 |
| 13. Roof Trusses |
C July 16, 2005 |
| 14. Roof Sheathing |
C July 30, 2005 |
| 15. Roofing Felt, Ice Guard |
C July 30, 2005. |
| 16. Shingles |
C September 9, 2005 |
| 17. Windows Installed |
C Aug 13, 2005 |
| 18. Insulation/Vapor Barrier |
C. October 29, 2005 |
| 19. Exterior Entry Doors |
C August 13, 2005 |
| 20. Soffit/Fascia |
C October 10, 2005 |
| 21. Siding |
C October 1, 2005 |
| 22.
Rough Plumbing (sub) |
C August 11, 2005 |
| 23. Rough Electrical (sub) |
C August 11, 2005 |
| 24. HVAC Installed (sub) |
C January, 27, 2006 |
| 25. Drywall Hung |
C October 29, 2005 |
| 26. Attic Insulation |
C November 1, 2005 |
| 27. Drywall Finished (sub) |
C December 7, 2005 |
| 28. Trim and Int. Doors |
C January 28, 2006 |
| 29. Floor Covering-Vinyl (sub) |
C January 22, 2006 |
| 30. Cabinets and Countertops |
C January 22, 2006 |
| 31. Floor Covering-Carpet (sub) |
C January 26, 2006 |
| 32. Finish Plumbing (sub) |
C January 23, 2006 |
| 33. Finish Electric (sub) |
C January 23, 2006 |
| 34. Ext Decks |
C |
| 35. Driveway (sub) |
C |
| 36. Sidewalk (sub) |
C |
| 37. Landscaping |
C August 19, 2006 |
| 38. Other |
|
| 39.FINISHED!! |
C August 19, 2006 |
|