C=Complete, N/A =Not Applicable
IP= In Progress, SUB=Subcontract
Click on each topic to see a photo associated with it.
| 1. Lot Purchase | C. February 4, 2005 |
| 2. Blueprints | C. circa April 15, 2005 |
| 3. Building Permits | C. circa April 19, 2005 |
| 4. Basement Excavation (sub) | C. May 13, 2004 |
| 5. Basement Walls (sub) | C. May 20, 2005 |
| 6. Basement Floor (sub) | C. May 24, 2005 |
| 7. Sewer/Water Lateral (sub) | C May 11, 2005 |
| 8. Electrical Pedestal (sub) | C June 14, 2005 |
| 9. Gas Hookup (sub) | C June 15, 2005 |
| 10. Basement Ext. Insulation | C June 2, 2005 |
| 11. Floor Deck Installed | C June 4, 2005 |
| 12. Exterior Wall/Sheathing | C July 2, 2005 |
| 13. Roof Trusses | C July 16, 2005 |
| 14. Roof Sheathing | C July 30, 2005 |
| 15. Roofing Felt, Ice Guard | C July 30, 2005. |
| 16. Shingles | C September 9, 2005 |
| 17. Windows Installed | C Aug 13, 2005 |
| 18. Insulation/Vapor Barrier | C. October 29, 2005 |
| 19. Exterior Entry Doors | C August 13, 2005 |
| 20. Soffit/Fascia | C October 10, 2005 |
| 21. Siding | C October 1, 2005 |
| 22. Rough Plumbing (sub) | C August 11, 2005 |
| 23. Rough Electrical (sub) | C August 11, 2005 |
| 24. HVAC Installed (sub) | C January, 27, 2006 |
| 25. Drywall Hung | C October 29, 2005 |
| 26. Attic Insulation | C November 1, 2005 |
| 27. Drywall Finished (sub) | C December 7, 2005 |
| 28. Trim and Int. Doors | C January 28, 2006 |
| 29. Floor Covering-Vinyl (sub) | C January 22, 2006 |
| 30. Cabinets and Countertops | C January 22, 2006 |
| 31. Floor Covering-Carpet (sub) | C January 26, 2006 |
| 32. Finish Plumbing (sub) | C January 23, 2006 |
| 33. Finish Electric (sub) | C January 23, 2006 |
| 34. Ext Decks | C |
| 35. Driveway (sub) | C |
| 36. Sidewalk (sub) | C |
| 37. Landscaping | C August 19, 2006 |
| 38. Other | |
| 39.FINISHED!! | C August 19, 2006 |