C=Complete, N/A =Not Applicable
IP= In Progress, SUB=Subcontract
Click on each topic to see a photo associated with it.
| 1. Lot Purchase | C. February 4, 2005 |
| 2. Blueprints | C. October 30, 2005 |
| 3. Building Permits | C. November 22, 2005 |
| 4. Basement Excavation (sub) | C. April 1, 2006 |
| 5. Basement Walls (sub) | C. November 24, 2005 |
| 6. Slab Floor (sub) | C. April 5, 2006 |
| 7. Sewer/Water Lateral (sub) | C. November 24, 2005 |
| 8. Electrical Pedestal (sub) | C. June 1, 2006 |
| 9. Gas Hookup (sub) | C. June 1, 2006 |
| 10. Basement Ext. Insulation | C. April 6, 2006 |
| 11. Floor Deck Installed | N/A |
| 12. Exterior Wall/Sheathing | C. April 27, 2006 |
| 13. Roof Trusses | C. May 12, 2006 |
| 14. Roof Sheathing | C. June 10, 2006 |
| 15. Roofing Felt, Ice Guard | C. June 10, 2006 |
| 16. Shingles | C. June 10, 2006 |
| 17. Windows Installed | C. June 17, 2006 |
| 18. Insulation/Vapor Barrier | C August 18, 2006 |
| 19. Exterior Entry Doors | C December 16, 2006 |
| 20. Soffit/Fascia | C. July 15, 2006 |
| 21. Siding | C. July 15, 2006 |
| 22. Rough Plumbing (sub) | C. June 1, 2006 |
| 23. Rough Electrical (sub) | C July 14, 2006 |
| 24. HVAC Installed (sub) | C July 14, 2006 |
| 25. Drywall Hung | C August 26, 2006 |
| 26. Attic Insulation | C November 4, 2006 |
| 27. Drywall Finished (sub) | C November 12, 2006 |
| 28. Trim and Int. Doors | C December 22, 2006 |
| 29. Floor Covering-Vinyl (sub) | C December 14, 2006 |
| 30. Cabinets and Countertops | C December 9, 2006 |
| 31. Floor Covering-Carpet (sub) | C December 22, 2006 |
| 32. Finish Plumbing (sub) | C December 19, 2006 |
| 33. Finish Electric (sub) | C December 27, 2006 |
| 35. Driveway (sub) | C circa October 2006 |
| 36. Sidewalk (sub) | C circa October 2006 |
| 37. Landscaping | C May 2007 |
| 38. Other | |
| 39.FINISHED!! | C December 22, 2006 |