|
C=Complete, N/A =Not Applicable
IP= In Progress, SUB=Subcontract
Click on each
topic to see a photo associated with it.
| 1.
Lot Purchase |
C. February 4, 2005 |
| 2.
Blueprints |
C. October 30, 2005 |
| 3. Building Permits |
C. November 22, 2005 |
| 4.
Basement Excavation (sub) |
C. April 1, 2006 |
| 5. Basement Walls (sub) |
C. November 24, 2005 |
| 6. Slab Floor (sub) |
C. April 5, 2006 |
| 7. Sewer/Water Lateral (sub) |
C. November 24, 2005 |
| 8.
Electrical Pedestal (sub) |
C. June 1, 2006 |
| 9. Gas Hookup (sub) |
C. June 1, 2006 |
| 10. Basement Ext. Insulation |
C. April 6, 2006 |
| 11.
Floor Deck Installed |
N/A |
| 12.
Exterior Wall/Sheathing |
C. April 27, 2006 |
| 13. Roof Trusses |
C. May 12, 2006 |
| 14.
Roof Sheathing |
C. June 10, 2006 |
| 15. Roofing Felt, Ice Guard |
C. June 10, 2006 |
| 16. Shingles |
C. June 10, 2006 |
| 17. Windows Installed |
C. June 17, 2006 |
| 18. Insulation/Vapor Barrier |
C August 18, 2006 |
| 19. Exterior Entry Doors |
C December 16, 2006 |
| 20. Soffit/Fascia |
C. July 15, 2006 |
| 21. Siding |
C. July 15, 2006 |
| 22.
Rough Plumbing (sub) |
C. June 1, 2006 |
| 23. Rough Electrical (sub) |
C July 14, 2006 |
| 24. HVAC Installed (sub) |
C July 14, 2006 |
| 25. Drywall Hung |
C August 26, 2006 |
| 26. Attic Insulation |
C November 4, 2006 |
| 27. Drywall Finished (sub) |
C November 12, 2006 |
| 28. Trim and Int. Doors |
C December 22, 2006 |
| 29. Floor Covering-Vinyl (sub) |
C December 14, 2006 |
| 30. Cabinets and Countertops |
C December 9, 2006 |
| 31. Floor Covering-Carpet (sub) |
C December 22, 2006 |
| 32. Finish Plumbing (sub) |
C December 19, 2006 |
| 33. Finish Electric (sub) |
C December 27, 2006 |
| |
|
| 35. Driveway (sub) |
C circa October 2006 |
| 36. Sidewalk (sub) |
C circa October 2006 |
| 37. Landscaping |
C May 2007 |
| 38. Other |
|
| 39.FINISHED!! |
C December 22, 2006 |
|