CONSTRUCTION STATUS AT 835 Third

 

C=Complete, N/A =Not Applicable

IP= In Progress, SUB=Subcontract

Click on each topic to see a photo associated with it.

1. Lot Purchase C. February 4, 2005
2. Blueprints C. October 30, 2005
3.  Building Permits C. November 22, 2005
4.  Basement Excavation (sub) C. April 1, 2006
5.  Basement Walls (sub) C. November 24, 2005
6. Slab Floor (sub) C. April 5, 2006
7.  Sewer/Water Lateral (sub) C. November 24, 2005
8.  Electrical Pedestal (sub) C. June 1, 2006
9.  Gas Hookup (sub) C. June 1, 2006
10.  Basement Ext. Insulation C. April 6, 2006
11. Floor Deck Installed N/A
12. Exterior Wall/Sheathing C. April 27, 2006
13. Roof Trusses C. May 12, 2006
14. Roof Sheathing C. June 10, 2006
15. Roofing Felt, Ice Guard C. June 10, 2006
16. Shingles C. June 10, 2006
17. Windows Installed C. June 17, 2006
18. Insulation/Vapor Barrier C August 18, 2006
19. Exterior Entry Doors C December 16, 2006
20. Soffit/Fascia C. July 15, 2006
21. Siding C. July 15, 2006
22. Rough Plumbing (sub) C. June 1, 2006
23. Rough Electrical (sub) C July 14, 2006
24. HVAC Installed (sub) C July 14, 2006
25. Drywall Hung C August 26, 2006
26. Attic Insulation C November 4, 2006
27. Drywall Finished (sub) C November 12, 2006
28. Trim and Int. Doors C December 22, 2006
29. Floor Covering-Vinyl (sub) C December 14, 2006
30. Cabinets and Countertops C December 9, 2006
31. Floor Covering-Carpet (sub) C December 22, 2006
32. Finish Plumbing (sub) C December 19, 2006
33. Finish Electric (sub) C December 27, 2006
   
35. Driveway (sub) C circa October 2006
36. Sidewalk (sub) C circa October 2006
37. Landscaping C May 2007
38. Other  
39.FINISHED!! C December 22, 2006