C=Complete, N/A =Not Applicable

IP= In Progress, SUB=Subcontract

Click on each topic to see a photo associated with it.

1. Lot Purchase C Circa late 2005
2. Blueprints C August 2006
3.  Building Permits C September 2006
4.  Basement Excavation (sub) C September 26, 2006
5.  Basement Walls (sub) C October 4, 2006
6. Slab Floor (sub) C October 19, 2006
7.  Sewer/Water Lateral (sub) C September 26, 2006
8.  Electrical Pedestal (sub) C November 2007
9.  Gas Hookup (sub) C November 2007
10.  Basement Ext. Insulation C October 7, 2006
11. Floor Deck Installed N/A
12. Exterior Wall/Sheathing C October 28, 2006
13. Roof Trusses C November 3, 2006
14. Roof Sheathing C November 4, 2006
15. Roofing Felt, Ice Guard C November 4, 2006
16. Shingles C April 21, 2007
17. Windows Installed C January 27, 2006
18. Insulation/Vapor Barrier C June 1, 2007
19. Exterior Entry Doors C June 1, 2007
20. Soffit/Fascia C July 2007
21. Siding C May 19, 2007
22. Rough Plumbing (sub) C March 2006
23. Rough Electrical (sub) C March 2006
24. HVAC Installed (sub) C
25. Drywall Hung C June 16, 2007
26. Attic Insulation C July 2007
27. Drywall Finished (US!!) C August 23, 2007
28. Trim and Int. Doors C January 5, 2008
29. Floor Covering-Vinyl (sub) N/A
30. Cabinets and Countertops C January 5, 2008
31. Floor Covering-Carpet (sub) N/A
32. Finish Plumbing (sub) C
33. Finish Electric (sub) C
   
35. Driveway (sub) IP
36. Sidewalk (sub) IP
37. Landscaping IP
38. Other  
39.FINISHED!! IP