616 Wadleigh
As of July 10, 2010 the lot has been stripped and the frost walls built and backfilled. Soon we will be working here full time.
July 16 and 17 2010
In preparation for the plumber and then the pouring of the slab we leveled the site. We hope to get the blue board down for the pour this coming week.
July 24th, 2010
Saturday we worked at 616 Wadleigh bailing the water out of the footing trenches and getting some foam insulation boards cut.
WOW!
Did I mention WOW??
This week we went from bare ground to a front door! OK, maybe it is a front door frame, but we laid down insulation for the slab, had the plumbers in, had the slab poured and after some ciphering we raised three walls. We are hitting it hard, trying to get as much done as soon as possible. To that end:
-Our next work days are Monday the 2nd (8:00) , Tuesday the 3rd (8:00), Wednesday the 4th (8:00), Friday the 6th (12:30) and Saturday the 7th (8:00) each day at 616 Wadleigh.
-Friday is just a little iffy, watch your inbox as I will let you know about any changes.
The past two weekends we got the OSB up on the exterior walls, framed up some interior walls, cleaned up and organized the trailer and secured the house with our temporary garage door.
The trusses have been delivered. We plumbed the interior walls, added the top plate and placed the first couple trusses this weekend.
We will erect the remainder of the trusses this week and could use a big turnout. If you are able to help, please do!
The week started with a load of trusses to conquer. Wow, those trusses were flying up to the roof, being set, and by week’s end all the trusses were up, facia board was nailed and OSB was on the roof! We will continue nailing the OSB and then progress to roofing.
Please note were are not working Friday and Saturday this week. Have a safe Labor Day Weekend.