509 West Cornell

The Latest

 

May 30, 2011 

The lot has been stripped and compacted.......the trailer has been moved.....AND....... the Porta-Potti is on the way!!  Yep, it is BUILD TIME at Habitat.

Check the main page for the latest on when we will need you! 

The Week of June 20th

The east and south walls are up and the garage floor, porch and rear stoop have been poured.  Our goal this week is to erect the remaining walls and sheath them.

The Week of June 27th

The exterior walls are all up and sheathed with OSB.  Next week we will begin putting up interior walls. 

The Week of July 4th

We “trued up” the exterior walls and plumbed and set interior walls this week.  Next week we will continue with the interior walls. 

Wednesday we will hopefully be informed when the trusses will be delivered.  We may be placing trusses Friday or the following Monday.  Stay tuned as we will need a good crew on that day.  We hope to have a crane from Jim Anderson at Ellis Stone construction for the trusses.  Jim has graciously “given us a lift” with the trusses in the past. 

August 4, 5  2011

After getting all the trusses up in near record time we started the truss tiedowns and facia.  We also put up the front porch supports and rafters.

August 8, 10  2011

We finished framing the porch roof, and put up the OSB on the roof on the east and north sides.

August 12, 13  2011

On Friday we were able get the OSB on the gables before rain set in. Saturday the rains quit and we finished all of the roof OSB.  Looking to be dry inside by the end of next week!

August 19, 20 2011 

The crew installed all the drip edge and felt this week.  The shingles are coming this Wednesday.   If you are experienced, or willing to learn please join us Wednesday, Friday and/or Saturday as we always need a big crew for roofing.

August 24, 26, 27 2011

The shingles came on Wednesday, and true to form Bruce and the crew had the roof finished Saturday.  Great work!

September 9, 10 2011

We had the UWSP Women's Basketball Team in for their annual volunteer day. GO POINTERS!!  Last year it was shingling, this year we kept the women grounded and they got the foam insulation up on the exterior walls.  Thanks!!

Week of September 19, 2011

We are ready to start the siding, having put on the ground break and starter strip this weekend.  Also finished the soffit, and got some of the fascia on....looks great.  Four of the  windows are also in.  We will finish windows, work on fascia , and get the siding going this week.  Siding while it it still relatively warm......priceless......

Week of September 26, 2011

The rest of the windows are in and we got a good start on the siding this week.  It looks to be a beautiful next several days and by next Sunday we hope to have the majority of  the siding up.  After that we will start working on ceiling drywall.

Week of October 3, 2011

We finished the majority of the siding last week with the help of a great group from Trinity Lutheran Church on Saturday. Thanks! We hope to complete the siding this week, then it will be time for ceiling drywall.

Week of October 10, 2011

This week we finished the siding.  In order to prepare for the ceiling dry wall we placed attic vents, blocking for the dry wall, and braced the trusses.  The dry wall will be delivered Monday, and after a bit more prep work we will start putting it up.

Week of October 17, 2011

We got the vapor barrier on the ceiling and started hanging drywall.  We also got some wall insulation in.

Week of October 31, 2011

We got the trees down, cut up, and mostly hauled away this week.  Nearly all of the ceiling drywall is hung.  We will continue with drywall this week.

Week of November 7, 2011

This week we finished the ceiling dry wall, placed the wall insulation and cleaned and organized another storage bin. We will finish the vapor barrier and start hanging dry wall this week.  Big news is the heat is on at the house!

Week of November 28, 2011

We have been working on the drywall and have about 3/4 of it up.  The home is really taking shape.

Week of December 5th, 2011

Almost all of the drywall is up.  After this week we will take a couple weeks off as the drywall finishers come in and work their magic.

April 14, 2012

We are back up and running!

 An eager bunch was awaiting Bruce at 8 AM Saturday, a total of 16. After some guidance and direction the group installed trim in the bathrooms, painted the kitchen, unboxed the cabinets, cleaned out the garage and hung about 50% of the garage drywall. They also staked out the new home at 525 West Cornell.

Week of April 16, 2012

This week we got a good start on the kitchen cabinets and finished hanging the dry wall in the garage.  We will continue on the cabinets this coming week and hope to get the excavator in to start the new home next door.  We plan on finishing 509 W Cornell by June and continue building 525 W. Cornell after that.

Week of April 23, 2012

The cabinets are in, black dirt has been spread, and we hope to start on the footings for the next home this week. We are looking to finish at 509      West Cornell in May, so we'll be busy next month.  Please join us if you can.

 Week of April 30, 2012

We continued trimming, mainly the exterior doors and utility room base.   Finished drywalling and painting the garage and the garage door went in Friday. Countertops are ordered and will be in the week of the 14th.  

Week of May 7, 2012

We got the belt sanding done on the kitchen counter and plan to glue it up and install Monday. We also finished the trim, installed TP holders, did some landscaping, and some layout for the plumbers at 525.

Our goal by Sat noon is to have 509 ready for carpet and 525 ready for heat tubes and concrete.