457 6th Avenue (2018)

Our next work days at 457 6th Ave in Stevens Point are Friday August 17th (8-4) and Saturday the 18th (8-12).

Current Progress

 

 

June 3, 2018

The lot has been stripped, sewer and water has been brought in, and about 600 yards of fill gives us a great start on our next home!
June 10, 2018

The garage footings have been poured, and the plumber has done the rough in. Next step is getting the foam down that will be under the slab. We will need volunteers this week for that….just not sure what day yet. Then we hope to pour the slab this week and begin framing at 8:00 on Friday June 15th. If you are able to help at anytime on Friday we would appreciate it, thanks.
June 15 2018

On Friday the rain stopped and our volunteers started. We had the first wall up in short order,

…….kept hammering away at it…..and by the end of the day all the exterior walls were up. What a great start!

June 22, 23 2018

We had a group from Cross Fit in Plover in on Friday and Saturday and got the interior walls up,

and got all the OSB and foam on….awaiting the installation of the trusses on Thursday.

June 28, 29 2018
Thursday and Friday (June 28, 29) we had a crane from Ellis Construction, and a crew from Heartland Custom Homes volunteering and the trusses, sheeting and roofing felt were completed. WOW! Great work, thank you!

August 11, 2018

While construction of our new home has been going great guns……thanks Brian and all the gang……our web-master has not.  To get us up to speed as of today, roof on, windows and doors in, most of siding done, wires pulled……and ready for insulation.  And…..drywall in a couple weeks.