457 6th Avenue (2018)

 

Our next work days  are Friday June 22nd (8:00 and into the afternoon) and Saturday June 23rd at 8:30.  Also, we plan on raising the trusses on Friday June 29th at 8:00, and we will need all the help we can get.

.

 

Current Progress

June 3, 2018

The lot has been stripped, sewer and water has been brought in, and about 600 yards of fill gives us a great start on our next home!
June 10, 2018

The garage footings have been poured, and the plumber has done the rough in. Next step is getting the foam down that will be under the slab. We will need volunteers this week for that….just not sure what day yet. Then we hope to pour the slab this week and begin framing at 8:00 on Friday June 15th. If you are able to help at anytime on Friday we would appreciate it, thanks.

June 15  2018

On Friday the rain stopped and our volunteers started.  We had the first wall up in short order,

…….kept hammering away at it…..and by the end of the day all the exterior walls were up. What a great start!